Project Buffer vs Feeding Buffer vs Resource Buffer

Project Buffer – A project buffer is inserted at the end of the project network between the last task and the completion date. Any delays on the longest chain of dependent tasks will consume some of the buffer but will leave the completion date unchanged and so protect the project. The project buffer is typically recommended to be half the size of the safety time taken out, resulting in a project that is planned to be 75% of a “traditional” project network.

Feeding Buffers – delays on paths of tasks feeding into the longest chain can impact the project by delaying a subsequent task on the Critical Chain. To protect against this, feeding buffers are inserted between the last task on a feeding path and the Critical Chain. The feeding buffer is typically recommended to be half the size of the safety time taken out of the feeding path.

Resource Buffers – Resource buffers can be set alongside of the Critical Chain to ensure that the appropriate people and skills are available to work on the Critical Chain tasks as soon as needed.